Woodland Village

The Zoning Board of Appeals issued a denial of the recent application for 200 rental units from the Applicant for Woodland Village. To see a copy of the denial please click here.

For more information on the Woodland Village 40B project please contact the Assistant Town Planner at 781-826-7641 or by email at communitypreservation@hanover-ma.gov

Timeline of Events of the Woodland Village project with links to pertinent documents.

DATE

EVENT

OCTOBER 2008

Town submits comments to Mass Housing concerning Site eligibility application.

August 27, 2009

Woodland Village receives Mass Housing Project Eligibility Approval Letter

October 22, 2009

Woodland Village Application Received by ZBA with check for $8,500 and letter contesting the application fees.

October 26, 2009

Town Planner sends copies of Woodland Village plans to Town Boards and Depts for review.

November 3, 2009

ZBA sends letter to Woodland Village that they cannot accept their application without the full filing fees

November 4, 2009

Comments received by ZBA from Doug Billings- Water Dept.

November 24, 2009

Hanover receives letter from DHCD confirming Hanover’s compliance with the Affordable Housing Plan from October 29, 2009 until October 28, 2011.

December 3, 2009

ZBA sends letter to Woodland Village stating they are in compliance with DHCD SHI.

December 3, 2009

Applicant sends in $29,500 check with letter objecting to fees and reserving right to appeal them for refund.

December 14, 2009

Selectmen send letter to ZBA with their review of the project

December 17, 2009

Woodland Village files appeal to Department of Housing and Community Development (DHCD).

December 22, 2009

Conservation Commission letter of review received.

December 23, 2009

Request from Woodland Village to continue hearing scheduled for December 28.

December 23, 2009

Review from W. Sweeney – Police Dept.

December 24, 2009

Review from B. Stone – Fire Dept.

December 28, 2009

ZBA Public Hearing Notice

December 28, 2009

Letter received from Jean Murphy (Abutter) with concerns about project.

December 28, 2009

Scheduled ZBA hearing – Letter sent to Woodland Village with amount needed for posting and mailing – Meeting rescheduled to February 8, 2010 at applicant’s request.

January 7, 2010

Town Counsel responds to applicant’s DHCD appeal.

January 12, 2010

Applicant  responds to Town Counsel’s  response.

February 2, 2010

Letter to ZBA from DHCD that case needs to go to Housing Appeals Committee (HAC)

February 3, 2010

Letter from applicant requesting continuance of February 8, 2010 hearing until March 1 or after

February 8, 2010

Scheduled ZBA hearing – continued until March 8, 2010.  

February 25, 2010

Applicant files initial pleading with HAC.

March 1, 2010

Letter from HAC to ZBA informing them of initial pleading by applicant. 

March 2, 2010

Letter from Town Counsel to Selectmen in response to their request for information. 

March 3, 2010

Letter from applicant indicating they will not be at March 8 hearing and consider to be in a stay until HAC decision. 

March 4, 2010

Town Counsel submits Notice of Appearance to HAC.

March 5, 2010

Con Com sends reminder letter to applicant about Con Com issues

March 8, 2010

Scheduled ZBA hearing – Continued to May 10, 2010.

April 29, 2010

Town Counsel submits motion for extension to file briefs to May 12, 2010 to HAC. 

May 10, 2010

Scheduled ZBA hearing – continued until June 14, 2010.

May 17, 2010

Town Counsel files brief with HAC. 

May 18, 2010

Applicant  files brief with HAC.

May 21, 2010

Town Counsel sends Town Planner a copy of the brief submitted by Hanover Woods LLC

June 14, 2010

Scheduled ZBA hearing – continued until July 28, 2010

June 21, 2010

HAC issues decision – Upholds fees, denies “safe harbor” – The applicant is responsible for the full fees, but the Town must accept the application as of the filing date. 

July 26, 2010

Zoning Board of Appeals Public hearing opened on the Woodland Village Comprehensive Permit Application.

August 4, 2010

ZBA sends notification to abutters about continuation of Woodland Village hearing to August 23, 2010.

August 23, 2010

Continuation of ZBA’s Public Hearing on Woodland Village.

September 20, 2010

Continuation of ZBA’s Public Hearing on Woodland Village.

October 5, 2010

Zoning Board of Appeals receives approval from MHP for technical assistance. 

October 18, 2010

ZBA opens meeting and votes to continue the public hearing on Woodland Village to November 15, 2010.

November 15, 2010

Continuation of ZBA’s Public Hearing on Woodland Village.  Motion is made and accepted to continue the public hearing on Woodland Village to December 20, 2010.

4-15-11

Developer submits revised plans for 152 units of for sale housing 

5-6-11

Developer submits revised plans for 252 units of rental housing

5-13-11

Jacobs Engineering submits traffic study peer review

May 23, 2011

Developer's response to peer review of traffic study

June 13, 2011

Response to Comprehensive Environmental Incorporated (CEI) Review of Site Plan , dated May 18, 2011: Letter from Hanover Woods; Figure A; Figure B

June 13, 2011

Conservation Commission's Comments on Woodland Village Project

September 28, 2011

Decision on Woodland Village Comprehensive Permit filed with Town Clerk.

October 18, 2011

Hanover Woods, LLC's Appeal of Comprehensive Permit with Conditions and Motion for Reduction in Filing Fee

October 28, 2011

Environmental Notification Form Submitted to MEPA
ENF Plans 1
ENF Plans 2

December 9, 2011

Applicant submits letter of Change of Notice to the HAC.

December 27, 2011

Letter to MEPA

December 29, 2011

ZBA Opposition to Notice of Change in Applicant's Proposal 11/4 Hanover Woods

March 14, 2012

Ruling on Notice of Project Change for Woodland Village

April 4, 2012

Public Hearing at 7:45 p.m., Large First Floor Hearing Room - Hearing Notice

March 22, 2012

Hanover Woods LLC submission of 200 Unit Comprehensive Permit Plan

April 12, 2012

Vanasse & Associates Traffic Impact Assessment
Connery Associates Impact Report

April 24, 2012

Con Com Revised 40B Letter to ZBA

April 24, 2012

Comprehensive Environmental Inc. Modification Review

April 24, 2012

Jacobs Traffic Review

April 25, 2012

DPW Memo to ZBA

April 25, 2012

At 7:45 p.m., Large First Floor Hearing Room - Continuation of public hearing on 200 unit plan.

April 25, 2012

Barbara Stone, Hanover Fire Department comments

April 26, 2012

Vanasse & Associates Response to Review Comments

May 4, 2012  

McKenzie Engineer Group, Inc. Response to Town Review Comments

May 4, 2012  

Grading Plans 1, 2, 3, 4, 5

May 15, 2012

At 7:45 p.m., Large First Floor Hearing Room - Continuation of public hearing on 200 unit plan.

June 11, 2012

7:45 p.m. – Continuation of public hearing for Woodland Village

June 28, 2012

ZBA Denial of project

July 17, 2012

Hanover Wood's Appeal of Decision on Remand

 