2024 Roadway Resurfacing and Paving Work
Resurfacing/Paving Improvements
![sign](https://www.hanover-ma.gov/sites/g/files/vyhlif12081/f/styles/news_image/public/pages/images.jpeg?itok=X5OuuJ_V)
Center Street
- Approximate Limits of Work: Broadway to Myrtle Street
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Mid-July
Main Street
- Approximate Limits of Work: Rosaria Lane to Stone Meadow Drive
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Mid-July